Home

Madras High Court Holds Post-Expiry Termination Invalid; Orders Refund of Forfeited Deposits with Interest

Copy LinkShareSave

A single-judge bench of Justice N. Anand Venkatesh heard an Arbitration Original Petition under Section 34(2) of the Arbitration and Conciliation Act, 1996, challenging an arbitral award that had upheld termination of a railway work contract and forfeiture of contractual deposits. The petition arose from disputes over a contract for a new foot over bridge at Chennai Egmore (platforms 2 to 11) and related claims and counterclaims between the contractor and the Divisional Railway Manager, Chennai Division.

The court allowed the petition in part, setting aside the arbitral tribunal's findings that justified termination of the contract and consequent forfeiture of the Earnest Money Deposit (EMD), Performance Guarantee (PG) and Security Deposit (SD). The High Court held that the contract had come to an end by efflux of time on 30.06.2020 and therefore could not be validly "terminated" thereafter; accordingly Claim Nos.1 to 4 and Claim No.7 were allowed in favour of the claimant. The Court directed refund of the EMD, PG and SD with interest at 9% per annum from 30.06.2020 until actual payment, and ordered payment of Rs.4,50,000 with similar interest for stock at site. The Court set aside the arbitral award insofar as counter claims 1 and 2 were allowed by the tribunal, while the rest of the award was confirmed; costs of Rs.2,00,000 were directed to be paid to the petitioner.

The Court, in its reasoning, observed: "Once a contract comes to an end by efflux of time and the period is not extended, there is no question of issuing a termination notice and thereafter terminating the contract. The very process of termination pre-supposes that there is a subsisting contract. If there is no subsisting contract, there is nothing to be terminated thereafter." The judgment also noted that an extension under GCC Clause 17A(ii) was granted for delays "not due to Railway or Contractor" and that such an extension did not render the contract subsisting beyond the extended period for the purpose of a later termination; the Court found the tribunal's justification for termination "clearly perverse and suffers from patent illegality."

Background

The dispute arose from an agreement dated 27.03.2017 for construction of a foot over bridge, with a 12‑month completion period, three extensions being granted the last time up to 30.06.2020 under Clause 17A(ii) of the General Conditions of Contract (GCC). The respondent issued a termination notice dated 30.09.2020 purportedly with effect from 30.06.2020, forfeited EMD, PG and SD, and rejected several claims of the contractor. The matter was referred to an Arbitral Tribunal which awarded only Price Variation and GST claims in favour of the claimant while upholding termination and awarding certain counterclaims for the respondent.

The petitioner challenged the award under Section 34, contending the termination was not valid because the contract had already expired by efflux of time and no further extension had been granted. The respondent maintained that the contractor had been in breach and justified termination under GCC 62(1) and forfeiture under Clause 16(4)(f). The High Court examined documentary evidence of progress reports, extension orders, the content of the termination notice and the tribunal's approach. The Court distinguished precedents relied upon by the tribunal (including Air India v. Gati) as inapplicable to the present facts and referred to prior decisions on expiry versus termination. It concluded that the tribunal erred in treating a post‑expiry action as termination and that forfeiture flowing from that finding was unsustainable. The Court confirmed that loss of profit claim (Claim No.11) could not be granted on a mechanical basis and therefore refused interference with the tribunal's rejection of that head. The final result: Claim Nos.1–4 and 7 were allowed; EMD, PG and SD and Rs.4,50,000 for stock at site were to be refunded with 9% interest from 30.06.2020; counterclaims 1 and 2 set aside; other parts of the award confirmed; petition allowed with costs of Rs.2,00,000.

Case Details: Case No.: Arb.OP(Com.Div).No.630 of 2022 Case Title: M/s. Sivashankar & Co Rep. by its Proprietor D. Sivashankar v. The Divisional Railway Manager, Chennai Division, Southern Railway, Chennai Appearances: For the Petitioner(s): Mr. J. Srinivasa Mohan, for M/s. TVJ Associates For the Respondent(s): Mr. K.S. Jayaganesan, Senior Counsel